Pumping and Conveyance System for Balance Quantity of 4th Phase Water, Under Greater Karachi Bulk Water Supply Scheme.


Actual Services provided by EA Consulting Pvt. Ltd:


Detail design review
Preparation of construction drawings
Preparation of PC-I
Construction management and supervision of the project work
Checking of materials, and workmanship of contractors
Verification of Contractor’s Invoices
Progress Reporting
Certifying completion of contracts. Supervision work comprises the following components
- Construction of additional pumping station at Dhabeji
- Construction of pumping station at Dumlottee and additional works at North East Karachi Pumping Station.
- Renovation of pumping stations at COD and Kidney Hills and making connections with existing trunk mains.
- Laying transmission mains of 84”, 66”, 54”& 33” diameter of PRCC Pipes.